2004 Classroom Remodeling
Common Area

    August 16, 2004
Photograph: Common Area, tack boards installed.
August 11, 2004
Photograph: Common Area, ready to move back furniture.
  August 11, 2004
Photograph: Common Area, ready to move back furniture.
August 6, 2004
Photograph: Common Area, wood base installed around columns.
  August 3, 2004
Photograph: Common Area, carpeting installed.
August 2, 2004
Photograph: Common Area, preparation prior to installing carpet.
  July 29, 2004
Photograph: Common Area, hallway leading to elevator painted and stained.